ANALISIS EARNED VALUE TERHADAP BIAYA DAN WAKTU GEDUNG DIREKTORAT POLITEKNIK PU SEMARANG DENGAN PRIMAVERA P6

Noel Eka Nugraha, Fajar Sri Handayani, Setiono Setiono

Abstract

Semarang PU Politeknik Building Construction Project is the construction of an educational building area developed in collaboration between PT Wika Gedung and PT Yodya Karya with a construction management consultant contract value of 3.9 billion and an executing contractor contract value of 281 billion. In this research, a research method with a quantitative descriptive approach was taken. This means that in this project, the condition of the project is described based on the analysis of the data obtained from the project. The data is then processed using descriptive and analytical methods. The Earned Value or EV concept method studies comparing the value of the work completed against the budget provided to carry out the work. The result of this research is to analyze using the Primavera P6 program whether the project is running at an appropriate cost and a schedule that does not deviate from the contract. The results of the analysis obtained for the implementation of the weekly analysis of the Earned Value indicator value obtained is positive which means that in the entire week of analysis, the project runs faster and more economically. The EAC and ETC values obtained are smaller than the contract cost, indicating that the project is planned to be completed at a smaller cost. The deviation value obtained is at an average of 0.08% with the smallest deviation being 0.0794% so the project will experience a profit of 8% on the completion date.

Keywords

Earned Value, Cost, Schedule, Primavera P6

Full Text:

PDF

References

Agnessia, dkk. (2022) Penerapan Metode Earned Value Analysis Menggunakan Software Primavera Project Planner Pada Pembangunan Instalasi Pengolahan Air Limbah. Journal Universitas Indraprasta PGRI.

Anwarsyah, dkk. (2019). Project Performance Analysis Using the Earned Value Management (EVM) Method. IPTEK Journal of Proceedings Series No. (5) (2019), ISSN (2354-6026).

Chan, dkk. (2002). Compressing construction durations: lessons learned from Hong Kong building projects. International journal of project management, 20(1), 23-35.

Istimawan, D. (1996). Manajemen Proyek & Konstruksi, Jilid 1. Kanisius.

Eirgash, M. A. (2019). Earned value analysis for construction projects using project management scheduling engine. American Journal of Civil Engineering, 7(5), 121-125.

Fleming, Q, W., Koppelman, J, M. (1994). The Essence and Evolution of Earned Value. Cost Engineering; Morgantown Vol. 36, Iss. 11.

Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.

Mockler, R. J. (1972). The Management Control Process. Appleton-Century-Crofts. New York.

Moradi, dkk. (2017). An Earned Value Model with Risk Analysis for Project Management Under Uncertain Conditions. Journal of Intelligent and Fuzzy Systems.

Nasir, A., Arif, M. (2011) Application of Earned Value Analysis in Construction Projects: A Case Study. Journal Civil Engineering Department, University Technology PETRONAS.

Nugraha, dkk. (1985). Manajemen Proyek Konstruksi. Surabaya Penerbit Kartika

Yuda. Lucya, O. (2018) Analisis Nilai Hasil (Earned Value Analysis) Terhadap Pengendalian Biaya dan Waktu Pembangunan Gedung Type B Gedung Wanita Kalibokor. Jurnal UNIM.

Pinto, dkk. (1995). Lessons for an accidental profession. Business Horizons, Volume 38, Issue 2.

PMBOK guide. (2004). A Guide to the Project Management Body of Knowledge. Third Edition. Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA.

Iman, S. (1995). Manajemen Proyek Dari Konseptual Sampai Operasional. Jakarta. Penerbit Erlangga.

Sudarsana, dkk. (2008). Pengendalian Biaya Dan Jadual Terpadu Pada Proyek Konstruksi. Jurnal Ilmiah, Universitas Udayana.

Terry, George Robert. (1953). Principles of Management. Homewood, Ill.: Richard D. Irwin, 1977.

Tolangi, dkk. (2012). Analisis Cash Flow Optimal Pada Kontraktor Proyek Pembangunan Perumahan. Jurnal Sipil Statik, Vol.1, No. 1, November 2012.

Turner, dkk. (2005). The Project Manager’s Leadership Style as a Success Factor on Projects. Project Management Journal 36(2):49-61.

Widayanti, dkk. (2017) Pengendalian Biaya dan Waktu dengan Menerapkan Metode Earned Value Analysis (EVA) Menggunakan Software Primavera Project Planner P6. Jurnal Matriks Teknik Sipil/Desember 2017/1458.

Yomelda., dkk. (2015) Analisa Earned Value pada Proyek Pembangunan Vimala Hills Villa dan Resort Bogor. Jurnal Teknik ITS Vol. 4, No. 1, (2015) ISSN: 2337-3539

Refbacks

  • There are currently no refbacks.