ANALISIS BIAYA DAN WAKTU MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PROYEK PEMBANGUNAN ARJUNO AGRO TECHNO PARK

Reky Muhamad Fairuz, Daimil Ihsan, Sucipto Sucipto

Abstract

In construction project management, cost and time are two crucial, interconnected elements. Delays in project completion and cost increases are common issues that are often encountered. This research aimed to evaluate and control the cost and time of the Arjuno Agro Techno Park development project using the Earned Value Management (EVM) method. EVM is an integrated method that combines scope, cost, and time measurements to objectively assess project performance. The primary focus of this study was to identify cost and time deviations from the initial plan and determine the project's performance status at specific periods.

The approach applied in this research was quantitative, involving data collection related to the Budget Estimate Plan, project schedule, and actual progress reports from the Arjuno Agro Techno Park project. The data was analyzed using EVM indicators such as, BCWS, ACWP, SV, CV, SPI, CPI, ETC, EAC, EAS, and ETS. The research findings indicated that the project experienced schedule delays, evidenced by an (SPI < 1) from the 7th to the 21st week. Nevertheless, the project was successfully completed in the 22nd week, which was initially targeted for completion in the 21st week. However, the project's completion cost tended to be more efficient compared to the initial contract value, as indicated by a (CPI > 1).

Keywords: Arjuno Agro Technopark; Earned Value Management (EVM); project cost; project performance; project time

References

Aditama, R. (2021). Analisis Biaya Dan Waktu Menggunakan Metode Evm (Earned Value Method) Pada Proyek Konstruksi (Studi Kasus Pada Proyek Pembangunan Gedung Laundry Rsud Sidaorjo). Universitas 17 Agustus 1945 Surabaya.

Anwar, S., & Hayati, N. I. (2013). Analisis Pemakaian Metode Earned Value Sebagai Alat Pengendalian Proyek. Astonjadro,2(2), 19–28.

Asmoro, M. R., Witjaksana, B., & Tjendani, H. T. (2024). Cost And Time Analysis Using Earned Value Method Building Construction Of Distance Learning Program Units Of Surabaya Open University Phase Ii. International Journal on Advanced Technology, Engineering, and Information System (IJATEIS), 3(1), 92–104. https://doi.org/10.55047/ijateis.v3i1.1020

Aulia, P. S., Yogaswara, B., & Suwarsono, L. W. (2018). Analisis Kinerja Pengelolaan Proyek Pembangunan Kantor Bkd Kab. Karanganyar Dengan Menggunakan Earned Value Method. Eproceedings Of Engineering, 5(3)

Borges, A. C., & Asa, M. F. (2023). Analisis Pengendalian Biaya Dan Waktu Menggunakan Metode Nilai Hasil (Earned Value) Pada Kasus Pembangunan Gedung Puskesmas Lumbang Di Kabupaten Probolinggo. Journal of Sustainable Infrastructure, 2(1), Article 1. https://doi.org/10.61078/jsi.v2i1.13

Dimyati, H., & Nurjaman, K. (2014). Manajemen Proyek. Pustaka Setia.

Fitria, A. D., Defiana, Y., & Sumarno, W. (2024). Analisis Pengendalian Waktu Dan Biaya Dengan Metode Earned Value Management (Evm): (Studi Kasus Pada Proyek Pembangunan Rkb Mts Negeri 15 Ciamis). Media Ilmiah Teknik Sipil, 1(2), Article 2. https://ojs.unigal.ac.id/index.php/miteks/article/view/3377

Hardianta, C., & Effendy, M. (2021). Penjadwalan Proyek Dengan Kurva S Berbasis Tenaga Kerja Pada Proyek Pembangunan Perumahan. Seminar Keinsinyuran Program Studi Program Profesi Insinyur, 1(2). https://doi.org/10.22219/skpsppi.v2i1.4434

Husen, A. (2009). Manajemen proyek (perencanaan,penjadwalan &pengendalian Proyek). C.V ANDI OFFSET.

Nurhayati. (2010). Manajemen Proyek. Yogyakarta: Graha Ilmu

Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., & Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3), 301. https://doi.org/10.3390/buildings12030301

Sentana, H. S., Suksmono, A. K., & Sari, C. A. N. (2024). Evaluasi Waktu Dan Biaya Menggunakan Earned Value Method (EVM) Pada Gedung Mal Pelayanan Publik (MPP) Kota Tegal. Jurnal Teknik Sipil Dan Bangunan, 2(1), 13–19. https://ojs.unsiq.ac.id/index.php/pasak/article/view/7886

Soeharto, Ir. I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional). Erlangga.

Soemardi, B. W., Abduh, M., Wirahadikusumah, R., & Pujoartanto, N. (2006). Konsep Earned Value untuk Pengelolaan Proyek Konstruksi. Institut Teknologi Bandung. https://scholar.google.com/citations?view_op=view_citation&hl=en&user=-knqiPcAAAAJ&citation_for_view=-knqiPcAAAAJ:kNdYIx-mwKoC

Witjaksana, B., & Reresi, S. P. (2012). Analisis Biaya Proyek Dengan Metode Earned Value Dalam Proses Kinerja (Studi Kasus Pada Proyek Pembangunan Universitas Katholik Widya Mandala Pakuwon Citi-Surabaya). Extrapolasi: Jurnal Teknik Sipil

Refbacks

  • There are currently no refbacks.